Cafe and restaurant fit-out approvals in Sydney: what needs sign-off before you open

The approvals behind a Sydney cafe or restaurant fit-out: planning consent, food premises rules, trade waste and licensing, in the order they happen. By KENURO architects.

KENURO architects

11/18/20262 min read

Vellune wine bar fit-out by KENURO architects, Sydney
Vellune wine bar fit-out by KENURO architects, Sydney

A cafe or restaurant has more approval steps than almost any other small commercial fit-out, because food, alcohol, exhaust and waste all touch a different authority. Here is what needs sign-off in Sydney, and the order that keeps it moving.

1. Planning consent: DA, CDC or exempt

First, confirm the premises can legally operate as a food premises. If the approved use is already a cafe or restaurant and your works are minor, part of the fit-out may proceed under exempt or complying pathways. A change of use, new mechanical exhaust, outdoor dining or work to a heritage item usually means a Development Application to council.

Some works can go through a Complying Development Certificate with a private certifier instead, which is typically much faster. When we fitted out Vellune, a 94 square metre wine bar in a historic Surry Hills building, we kept the existing layout specifically because changing it would have triggered a DA. The project proceeded on a CDC and was built in seven weeks. Choosing the pathway early is one of the biggest schedule decisions you make.

2. Food premises requirements

Food businesses must notify and register with the local council before trading, and the fit-out itself must meet the food premises standard AS 4674, which covers washable surfaces, layout of food preparation areas, handwashing facilities, storage and pest control. Council environmental health officers can inspect during the build and before opening, so the drawings need to get these details right from the start, not patched at the end.

3. Trade waste and grease arrestors

Any kitchen discharging to sewer needs a trade waste agreement with Sydney Water, and most cooked-food premises need a grease arrestor sized to the menu and equipment. The arrestor has a physical size and a service clearance, and finding space for it is a design problem that should be solved at concept stage, not discovered on site.

4. Mechanical exhaust and ventilation

Cooking equipment needs a mechanical exhaust system designed to the relevant standards, and its discharge point matters: councils and certifiers look closely at where kitchen exhaust terminates, especially near residences. In many buildings the riser path and roof plant need landlord consent as well as approval.

5. Liquor licensing

If you plan to serve alcohol, the liquor licence is a separate application through Liquor & Gaming NSW, with its own consultation and timing. It runs in parallel with the fit-out approvals, not after them, and it can gate your opening date if left late.

6. Fire safety and accessibility

The fit-out must maintain the building's fire safety measures, and any new work is checked against the access requirements of the Building Code and AS 1428.1: entries, circulation, amenities and, for larger venues, accessible toilets.

The order that works

Confirm the approved use, pick the planning pathway, design the kitchen and exhaust to the food premises standard, lodge the trade waste application early, and run the liquor licence in parallel. The venues that open on time are the ones where these tracks started together.