How long does DA approval take in Sydney? What the data says, and what speeds it up

Current NSW determination times, what happens inside those months, and the steps that keep your development application moving. By KENURO architects.

KENURO architects

11/18/20262 min read

Hamilton Road clinic fit-out by KENURO architects, Sydney
Hamilton Road clinic fit-out by KENURO architects, Sydney

If your project needs a Development Application, the honest question is how long council will take. There is now good public data on this, and it is more encouraging than the reputation suggests.

What the current data shows

The NSW Government's Council League Table, which tracks every council's assessment performance, shows development applications across NSW were determined in an average of 83 days in the last financial year: under three months, and a 24 per cent improvement on the year before. Councils determine around 85 per cent of all DAs in the state.

Councils have a statutory assessment period of 40 days for a standard DA, but the clock pauses whenever more information is requested, and referral and notification steps add weeks either side. That gap between the statutory period and the real-world average is where most projects lose time.

That is an average, and averages hide range. A straightforward shop fit-out change of use and a contested new house in a conservation area are both DAs, but they do not take the same time. Your council's own published average is the better guide for your project, and the same council league table publishes it.

Where the time actually goes

1. Lodgement and initial check. The application goes in through the NSW Planning Portal. Incomplete applications are not accepted, so the clock only starts on a complete set.

2. Notification and referrals. Neighbours are notified and, depending on the site, the application may be referred internally or to state agencies. Submissions and referral responses take weeks, and they are part of the statutory process.

3. Assessment and requests for information. If the planner needs more detail, they issue a request for information. The assessment clock effectively pauses while you answer, and slow or partial answers are the single most common cause of blown-out timeframes.

4. Determination. Approval usually comes with conditions. Read them before you celebrate: conditions can require amended drawings or further approvals before construction.

What speeds a DA up

• Lodge complete. Accurate drawings, the right reports and a thorough statement of environmental effects avoid the first request for information.

• Design to the controls. Applications that comply with height, setback and parking controls sail past the ones that argue with them. Where a variation is needed, justify it tightly.

• Use the pre-lodgement meeting. Most Sydney councils offer pre-DA advice. Issues surfaced there are cheap; issues surfaced mid-assessment are not.

• Answer RFIs fast and fully. Days here are the cheapest days you can buy on the whole project.

• Consider whether you need a DA at all. Many fit-outs and some homes qualify for a Complying Development Certificate through a private certifier, which by rule must be decided within 10 to 20 days of a complete application. Our separate post on choosing between CDC and DA covers how that decision is made.

After the DA

Consent is not the end. Most projects then need a Construction Certificate before building starts, and a principal certifier inspects during the works. Factor both into the program, and keep your documentation consistent so the CC is a formality rather than a redesign.